The Specialty:
Bored Piles
by
Foundation Specialists
Bored piles are cast in place cylindrical piles excavated
either by use of rotary equipment operated augers , buckets, under static drilling fluid or large drill bit (for hard rock) with
reverse circulation, with chisel grab and casing oscillator for bouldery ground, with large diameter DTH hammers and compressed air (drilled piles), among others.
Most common
large diameter bored piles, are installed through an overburden of cohesive or cohesionless soil strata, with or without water tale, down to firmer ground, to achieve the design bearing capacity by skin friction, base bearing or both, to serve as foundation piles for residential, commercial, institutional
buildings, industrial complexes or infrastructures.
Bored piles installed in common soil with the presence of water table, generally require the use of a short temporary steel casing and a drilling fluid as static
suspension to provide support to the surrounding soil while excavating the pile and until complete
backfill of the pile excavation with concrete, in order to prevent cave-in of the excavation and destabilizing the surrounding
soil formation.
The preparation and handling by most effective drilling fluid, Bentonite Mud, is a sophisticated
technology by itself and requires a complete set up of dedicated equipment and (basic) field laboratory.
The most common diameters of bored piles range from
0.6 meter to 2.0 m meters, likewise length can range from few meter to sixty or more meters, depending upon design
loads and soil parameters.
Bored piles can be heavily reinforced if required by design, rebar cages usually are prefabricated in segments with length and weight depending upon available commercial lengths
of rebars and available lifting equipment. Splicing of rebar cages can be done by lap
splice, welded lap splice or mechanical threaded couplers. Casting is done by pouring concrete with the design strength and
slump as required, through watertight segmental Tremie Pipes, starting from the pile bottom and letting the tremie pipe bottom end remain at least 3 meters submerged in concrete until the completion of pouring, to guarantee the pile continuity
and the final good quality of the concrete cast.
Drilling fluids, if needed, can be water, a suspension of bentonite (bentonite
mud), a suspension of polymers, depending upon soil type, soil conditions, presence and elevation of water table,
chemical properties of water table (Ph, Salinity).
Steel casings can be temporary, in which case the wall thickness is usually big enough toallow many uses, are provided with collars for easy handling by vibro hammers and diameter
slightly larger than bored piles’ nominal diameter, to allow easy passage of drilling tools.
Permanent casings, if needed, are sacrificial casings and as such the wall thickness is as small as allowed by the
need to drive the casing through the ground.
Bored piles are commonly employed for bridge foundations, on land and water, because the versatility of bored piles design and execution allows the construction of practically
any needed diameter, including the very large diameters, and the pile reinforcement can be provided as heavy as needed by
seismic design and the codes (it is not uncommon to have double wall rebar cages in order to accommodate all the needed bars,
however care shall be taken to leave sufficient space between bars for concrete to low through).
Bored piles are also used to form retaining walls (see PileWall.com), as contiguous pile wall or secant pile wall or aligned pile wall, with or without post tensioned soil anchors as tie back .
Bored piles testing is usually done in two (2) stages, first stage testing to verify design assumptions and achievable design load , is done before starting the execution of the working piles: test piles are installed in the proposed construction area, as per design, and tested, first for integrity and continuity by P.I.T. (Pile Integrity
Test) then for load bearing capacity , either by Static Load Test or by Dynamic Load Test PDA, (Pile Dynamic Analysis). At times the Designer might require a Pull-out test and a lateral load test.
Once the design pile capacity has been confirmed, Bored Piles construction for the
working piles starts and quality control is then done on representative piles. Quality Control consists of testing the material used for the bored piles, i.e. reinforcing
bars and concrete, then testing of the piles at random with PIT and PDA, and predetermined
piles with static pile load test. Predetermined piles can also be tested using the cross-hole ultrasonic test, by inserting instruments through vertical pipes installed within the reinforcing steel cage
all throughout the bored pile length.